RailwaysIPM · Central Project +8.2% overrun#709814

NIPANIA-BHATAPRA [14.4 KM] 4TH LINE [PB-72/NR/2022-23]

Ministry of RailwaysChhattisgarh
Revised Cost: ₹184 CrUtilization: 0.0%Overrun: +₹14 Cr

Original Cost

₹170 Cr

Baseline estimate

+8% overrun

Revised Cost

₹184 Cr

Latest approved cost

Expenditure

₹0 Cr

Spent to date

Utilization

0.0%

Of revised budget

Escalated

Cost Status

+8.2%

+₹14 Cr increase

Remaining

₹184 Cr

Budget left

Budget Utilization

0.0%
0%25%50%75%100%

Spent

₹0 Cr

Remaining

₹184 Cr

Total

₹184 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹170 Cr

Revised Cost

₹184 Cr

Increase

+₹14 Cr

Escalation

+8.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2026

Revised Completion

31/12/2026

Completed

Project Details

Project Code709814
SectorRailways
MinistryMinistry of Railways
StateChhattisgarh
Data Month2025-09

Financial Summary

Original Cost₹170 Cr
Revised Cost₹184 Cr
Expenditure₹0 Cr
Original End Date31/12/2026
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹14 Cr (8.2%) from the original estimate of ₹170 Cr.

Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.

Remaining budget: ₹184 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

NIPANIA-BHATAPRA [14.4 KM] 4TH LINE [PB-72/NR/2022-23] is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹170.00 Cr, later revised to ₹184.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "NIPANIA-BHATAPRA [14.4 KM] 4TH LINE [PB-72/NR/2022-23]"?
NIPANIA-BHATAPRA [14.4 KM] 4TH LINE [PB-72/NR/2022-23] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Chhattisgarh. Original cost: ₹170 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹170 Cr and has been revised to ₹184 Cr — a cost overrun of +8.2%. Expenditure to date: ₹0 Cr (N/A% of revised cost). Data as of 2025-09.
QWhich ministry is responsible for this project?
NIPANIA-BHATAPRA [14.4 KM] 4TH LINE [PB-72/NR/2022-23] is under the Ministry of Railways in the Railways sector. Project code: 709814. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. NIPANIA-BHATAPRA [14.4 KM] 4TH LINE [PB-72/NR/2022-23] is one of several Bihar projects tracked under the Railways sector on the IPM system.