RailwaysIPM · Central Project +61.5% overrun#705933

Nimach-Ratlam 133 km

Ministry of RailwaysMadhya Pradesh
Revised Cost: ₹1771 CrUtilization: 84.5%Overrun: +₹675 Cr

Original Cost

₹1096 Cr

Baseline estimate

+62% overrun

Revised Cost

₹1771 Cr

Latest approved cost

Expenditure

₹1496 Cr

Spent to date

Utilization

84.5%

Of revised budget

Escalated

Cost Status

+61.5%

+₹675 Cr increase

Remaining

₹274 Cr

Budget left

Budget Utilization

84.5%
0%25%50%75%100%

Spent

₹1496 Cr

Remaining

₹274 Cr

Total

₹1771 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1096 Cr

Revised Cost

₹1771 Cr

Increase

+₹675 Cr

Escalation

+61.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/10/2027

Revised Completion

31/10/2027

Completed

Project Details

Project Code705933
SectorRailways
MinistryMinistry of Railways
StateMadhya Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1096 Cr
Revised Cost₹1771 Cr
Expenditure₹1496 Cr
Original End Date31/10/2027
Revised Date31/10/2027

Project Intelligence

Cost has increased by ₹675 Cr (61.5%) from the original estimate of ₹1096 Cr.

Expenditure stands at ₹1496 Cr, which is 84.5% of the revised project cost.

Remaining budget: ₹274 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Nimach-Ratlam 133 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1096.00 Cr, later revised to ₹1770.58 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Nimach-Ratlam 133 km"?
Nimach-Ratlam 133 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Madhya Pradesh. Original cost: ₹1096 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1096 Cr and has been revised to ₹1771 Cr — a cost overrun of +61.5%. Expenditure to date: ₹1496 Cr (84.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Nimach-Ratlam 133 km is under the Ministry of Railways in the Railways sector. Project code: 705933. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Nimach-Ratlam 133 km is one of several Bihar projects tracked under the Railways sector on the IPM system.