RailwaysIPM · Central Project +80.9% overrun#705764

Nimach-Badi Sadri NL Project 48 km

Ministry of RailwaysRajasthan
Revised Cost: ₹896 CrUtilization: 64.4%Overrun: +₹401 Cr

Original Cost

₹495 Cr

Baseline estimate

+81% overrun

Revised Cost

₹896 Cr

Latest approved cost

Expenditure

₹577 Cr

Spent to date

Utilization

64.4%

Of revised budget

Escalated

Cost Status

+80.9%

+₹401 Cr increase

Remaining

₹319 Cr

Budget left

Budget Utilization

64.4%
0%25%50%75%100%

Spent

₹577 Cr

Remaining

₹319 Cr

Total

₹896 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹495 Cr

Revised Cost

₹896 Cr

Increase

+₹401 Cr

Escalation

+80.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2026

Revised Completion

30/06/2026

Completed

Project Details

Project Code705764
SectorRailways
MinistryMinistry of Railways
StateRajasthan
Data Month2026-08

Financial Summary

Original Cost₹495 Cr
Revised Cost₹896 Cr
Expenditure₹577 Cr
Original End Date31/03/2026
Revised Date30/06/2026

Project Intelligence

Cost has increased by ₹401 Cr (80.9%) from the original estimate of ₹495 Cr.

Expenditure stands at ₹577 Cr, which is 64.4% of the revised project cost.

Remaining budget: ₹319 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Nimach-Badi Sadri NL Project 48 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹495.00 Cr, later revised to ₹895.67 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Nimach-Badi Sadri NL Project 48 km"?
Nimach-Badi Sadri NL Project 48 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Rajasthan. Original cost: ₹495 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹495 Cr and has been revised to ₹896 Cr — a cost overrun of +80.9%. Expenditure to date: ₹577 Cr (64.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Nimach-Badi Sadri NL Project 48 km is under the Ministry of Railways in the Railways sector. Project code: 705764. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Nimach-Badi Sadri NL Project 48 km is one of several Bihar projects tracked under the Railways sector on the IPM system.