New Railway Line between Ginigera and Raichur [165.57 km]
Original Cost
₹2565 Cr
Baseline estimate
Revised Cost
₹3035 Cr
Latest approved cost
Expenditure
₹2412 Cr
Spent to date
Utilization
79.5%
Of revised budget
Cost Status
+18.3%
+₹470 Cr increase
Remaining
₹623 Cr
Budget left
Budget Utilization
79.5%Spent
₹2412 Cr
Remaining
₹623 Cr
Total
₹3035 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2565 Cr
Revised Cost
₹3035 Cr
Increase
+₹470 Cr
Escalation
+18.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2019
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹470 Cr (18.3%) from the original estimate of ₹2565 Cr.
Expenditure stands at ₹2412 Cr, which is 79.5% of the revised project cost.
Remaining budget: ₹623 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
New Railway Line between Ginigera and Raichur [165.57 km] is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹2565.00 Cr, later revised to ₹3034.98 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "New Railway Line between Ginigera and Raichur [165.57 km]"?
- New Railway Line between Ginigera and Raichur [165.57 km] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Karnataka. Original cost: ₹2565 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2565 Cr and has been revised to ₹3035 Cr — a cost overrun of +18.3%. Expenditure to date: ₹2412 Cr (79.5% of revised cost). Data as of 2026-06.
- QWhich ministry is responsible for this project?
- New Railway Line between Ginigera and Raichur [165.57 km] is under the Ministry of Railways in the Railways sector. Project code: 705434. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. New Railway Line between Ginigera and Raichur [165.57 km] is one of several Bihar projects tracked under the Railways sector on the IPM system.