RailwaysIPM · Central Project +18.3% overrun#705434

New Railway Line between Ginigera and Raichur [165.57 km]

Ministry of RailwaysKarnataka
Revised Cost: ₹3035 CrUtilization: 79.5%Overrun: +₹470 Cr

Original Cost

₹2565 Cr

Baseline estimate

+18% overrun

Revised Cost

₹3035 Cr

Latest approved cost

Expenditure

₹2412 Cr

Spent to date

Utilization

79.5%

Of revised budget

Escalated

Cost Status

+18.3%

+₹470 Cr increase

Remaining

₹623 Cr

Budget left

Budget Utilization

79.5%
0%25%50%75%100%

Spent

₹2412 Cr

Remaining

₹623 Cr

Total

₹3035 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2565 Cr

Revised Cost

₹3035 Cr

Increase

+₹470 Cr

Escalation

+18.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2019

Revised Completion

31/03/2027

Completed

Project Details

Project Code705434
SectorRailways
MinistryMinistry of Railways
StateKarnataka
Data Month2026-06

Financial Summary

Original Cost₹2565 Cr
Revised Cost₹3035 Cr
Expenditure₹2412 Cr
Original End Date31/03/2019
Revised Date31/03/2027

Project Intelligence

Cost has increased by ₹470 Cr (18.3%) from the original estimate of ₹2565 Cr.

Expenditure stands at ₹2412 Cr, which is 79.5% of the revised project cost.

Remaining budget: ₹623 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

New Railway Line between Ginigera and Raichur [165.57 km] is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹2565.00 Cr, later revised to ₹3034.98 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "New Railway Line between Ginigera and Raichur [165.57 km]"?
New Railway Line between Ginigera and Raichur [165.57 km] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Karnataka. Original cost: ₹2565 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2565 Cr and has been revised to ₹3035 Cr — a cost overrun of +18.3%. Expenditure to date: ₹2412 Cr (79.5% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
New Railway Line between Ginigera and Raichur [165.57 km] is under the Ministry of Railways in the Railways sector. Project code: 705434. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. New Railway Line between Ginigera and Raichur [165.57 km] is one of several Bihar projects tracked under the Railways sector on the IPM system.