Original Cost
₹2565 Cr
Baseline estimate
Revised Cost
₹3035 Cr
Latest approved cost
Expenditure
₹2374 Cr
Spent to date
Utilization
78.2%
Of revised budget
Cost Status
+18.3%
+₹470 Cr increase
Remaining
₹661 Cr
Budget left
Spent
₹2374 Cr
Remaining
₹661 Cr
Total
₹3035 Cr
Original Cost
₹2565 Cr
Revised Cost
₹3035 Cr
Increase
+₹470 Cr
Escalation
+18.3%
Project Approved
Construction / Implementation
Original End Date
31/03/2019
Revised Completion
31/03/2027
Completed
Cost has increased by ₹470 Cr (18.3%) from the original estimate of ₹2565 Cr.
Expenditure stands at ₹2374 Cr, which is 78.2% of the revised project cost.
Remaining budget: ₹661 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.