Original Cost
₹2865 Cr
Baseline estimate
Revised Cost
₹2865 Cr
Latest approved cost
Expenditure
₹1 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2864 Cr
Budget left
Spent
₹1 Cr
Remaining
₹2864 Cr
Total
₹2865 Cr
Project Approved
Construction / Implementation
Original End Date
18/08/2030
Revised Completion
Completed
Project is within original budget of ₹2865 Cr — no cost escalation recorded.
Expenditure stands at ₹1 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹2864 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.