to Galgalia [Thakurgunj]
Original Cost
₹2650 Cr
Baseline estimate
Revised Cost
₹4412 Cr
Latest approved cost
Expenditure
₹4152 Cr
Spent to date
Utilization
94.1%
Of revised cost
Cost Overrun
+66.5%
+₹1762 Cr
Remaining
₹260 Cr
Budget left
Spent
₹4152 Cr
Remaining
₹260 Cr
Total
₹4412 Cr
94.1%
Utilized
Original Cost
₹2650 Cr
Revised Cost
₹4412 Cr
Increase
+₹1762 Cr
Escalation
+66.5%
Project Approved
Construction / Implementation
Original End Date
2024-12-31
Revised Completion
2025-07-11
Completed
Cost has increased by ₹1762 Cr (66.5%) from the original estimate of ₹2650 Cr.
Expenditure stands at ₹4152 Cr, which is 94.1% of the revised project cost.
Remaining budget: ₹260 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.