RailwaysIPM · Central Project +0.1% overrun#611943

New BG line between Naliya - Jakhau Port 24.88 Km

Ministry of RailwaysGujarat
Revised Cost: ₹410 CrUtilization: 2.9%Overrun: +₹0 Cr

Original Cost

₹410 Cr

Baseline estimate

+0% overrun

Revised Cost

₹410 Cr

Latest approved cost

Expenditure

₹12 Cr

Spent to date

Utilization

2.9%

Of revised budget

Escalated

Cost Status

+0.1%

+₹0 Cr increase

Remaining

₹398 Cr

Budget left

Budget Utilization

2.9%
0%25%50%75%100%

Spent

₹12 Cr

Remaining

₹398 Cr

Total

₹410 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹410 Cr

Revised Cost

₹410 Cr

Increase

+₹0 Cr

Escalation

+0.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/01/2028

Revised Completion

28/02/2028

Completed

Project Details

Project Code611943
SectorRailways
MinistryMinistry of Railways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹410 Cr
Revised Cost₹410 Cr
Expenditure₹12 Cr
Original End Date31/01/2028
Revised Date28/02/2028

Project Intelligence

Cost has increased by ₹0 Cr (0.1%) from the original estimate of ₹410 Cr.

Expenditure stands at ₹12 Cr, which is 2.9% of the revised project cost.

Remaining budget: ₹398 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

New BG line between Naliya - Jakhau Port 24.88 Km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹410.00 Cr, later revised to ₹410.26 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "New BG line between Naliya - Jakhau Port 24.88 Km "?
New BG line between Naliya - Jakhau Port 24.88 Km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Gujarat. Original cost: ₹410 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹410 Cr and has been revised to ₹410 Cr — a cost overrun of +0.1%. Expenditure to date: ₹12 Cr (2.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
New BG line between Naliya - Jakhau Port 24.88 Km is under the Ministry of Railways in the Railways sector. Project code: 611943. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. New BG line between Naliya - Jakhau Port 24.88 Km is one of several Bihar projects tracked under the Railways sector on the IPM system.