RailwaysIPM · Central Project +42.7% overrun#705629

Narayangarh - Bhadrak - 3rd line 155 km

Ministry of RailwaysWest Bengal
Revised Cost: ₹3425 CrUtilization: 85.5%Overrun: +₹1025 Cr

Original Cost

₹2400 Cr

Baseline estimate

+43% overrun

Revised Cost

₹3425 Cr

Latest approved cost

Expenditure

₹2927 Cr

Spent to date

Utilization

85.5%

Of revised budget

Escalated

Cost Status

+42.7%

+₹1025 Cr increase

Remaining

₹498 Cr

Budget left

Budget Utilization

85.5%
0%25%50%75%100%

Spent

₹2927 Cr

Remaining

₹498 Cr

Total

₹3425 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2400 Cr

Revised Cost

₹3425 Cr

Increase

+₹1025 Cr

Escalation

+42.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2025

Revised Completion

31/01/2027

Completed

Project Details

Project Code705629
SectorRailways
MinistryMinistry of Railways
StateWest Bengal
Data Month2026-08

Financial Summary

Original Cost₹2400 Cr
Revised Cost₹3425 Cr
Expenditure₹2927 Cr
Original End Date31/12/2025
Revised Date31/01/2027

Project Intelligence

Cost has increased by ₹1025 Cr (42.7%) from the original estimate of ₹2400 Cr.

Expenditure stands at ₹2927 Cr, which is 85.5% of the revised project cost.

Remaining budget: ₹498 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Narayangarh - Bhadrak - 3rd line 155 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹2400.00 Cr, later revised to ₹3425.32 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Narayangarh - Bhadrak - 3rd line 155 km"?
Narayangarh - Bhadrak - 3rd line 155 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: West Bengal. Original cost: ₹2400 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2400 Cr and has been revised to ₹3425 Cr — a cost overrun of +42.7%. Expenditure to date: ₹2927 Cr (85.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Narayangarh - Bhadrak - 3rd line 155 km is under the Ministry of Railways in the Railways sector. Project code: 705629. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Narayangarh - Bhadrak - 3rd line 155 km is one of several Bihar projects tracked under the Railways sector on the IPM system.