RailwaysIPM · Central Project +102.0% overrun#705410

Nangal Dam-Talwara 83.74 km - New broad gauge line & taking over siding Mukerian-Talwara 29.16 km

Ministry of RailwaysPunjab
Revised Cost: ₹4076 CrUtilization: 73.6%Overrun: +₹2058 Cr

Original Cost

₹2018 Cr

Baseline estimate

+102% overrun

Revised Cost

₹4076 Cr

Latest approved cost

Expenditure

₹2999 Cr

Spent to date

Utilization

73.6%

Of revised budget

Escalated

Cost Status

+102.0%

+₹2058 Cr increase

Remaining

₹1077 Cr

Budget left

Budget Utilization

73.6%
0%25%50%75%100%

Spent

₹2999 Cr

Remaining

₹1077 Cr

Total

₹4076 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2018 Cr

Revised Cost

₹4076 Cr

Increase

+₹2058 Cr

Escalation

+102.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2025

Revised Completion

31/12/2027

Completed

Project Details

Project Code705410
SectorRailways
MinistryMinistry of Railways
StatePunjab
Data Month2026-08

Financial Summary

Original Cost₹2018 Cr
Revised Cost₹4076 Cr
Expenditure₹2999 Cr
Original End Date31/12/2025
Revised Date31/12/2027

Project Intelligence

Cost has increased by ₹2058 Cr (102.0%) from the original estimate of ₹2018 Cr.

Expenditure stands at ₹2999 Cr, which is 73.6% of the revised project cost.

Remaining budget: ₹1077 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Nangal Dam-Talwara 83.74 km - New broad gauge line & taking over siding Mukerian-Talwara 29.16 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹2018.00 Cr, later revised to ₹4076.15 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Nangal Dam-Talwara 83.74 km - New broad gauge line & taking over siding Mukerian"?
Nangal Dam-Talwara 83.74 km - New broad gauge line & taking over siding Mukerian-Talwara 29.16 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Punjab. Original cost: ₹2018 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2018 Cr and has been revised to ₹4076 Cr — a cost overrun of +102%. Expenditure to date: ₹2999 Cr (73.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Nangal Dam-Talwara 83.74 km - New broad gauge line & taking is under the Ministry of Railways in the Railways sector. Project code: 705410. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Nangal Dam-Talwara 83.74 km - New broad gauge line & taking is one of several Bihar projects tracked under the Railways sector on the IPM system.