Original Cost
₹359 Cr
Baseline estimate
Revised Cost
₹359 Cr
Latest approved cost
Expenditure
₹40 Cr
Spent to date
Utilization
11.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹319 Cr
Budget left
Spent
₹40 Cr
Remaining
₹319 Cr
Total
₹359 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2028
Revised Completion
28/03/2028
Completed
Project is within original budget of ₹359 Cr — no cost escalation recorded.
Expenditure stands at ₹40 Cr, which is 11.1% of the revised project cost.
Remaining budget: ₹319 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.