Original Cost
₹262 Cr
Baseline estimate
Revised Cost
₹262 Cr
Latest approved cost
Expenditure
₹388 Cr
Spent to date
Utilization
148.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹0 Cr
Budget left
Spent
₹388 Cr
Remaining
₹0 Cr
Total
₹262 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
31/03/2026
Completed
Project is within original budget of ₹262 Cr — no cost escalation recorded.
Expenditure stands at ₹388 Cr, which is 148.0% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.