Miyagam-Karjan-Dabhoi-Samlaya 96.46 km- Gauge conversion with electrification
Original Cost
₹484 Cr
Baseline estimate
Revised Cost
₹1015 Cr
Latest approved cost
Expenditure
₹887 Cr
Spent to date
Utilization
87.4%
Of revised budget
Cost Status
+109.7%
+₹531 Cr increase
Remaining
₹128 Cr
Budget left
Budget Utilization
87.4%Spent
₹887 Cr
Remaining
₹128 Cr
Total
₹1015 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹484 Cr
Revised Cost
₹1015 Cr
Increase
+₹531 Cr
Escalation
+109.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
25/12/2026
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹531 Cr (109.7%) from the original estimate of ₹484 Cr.
Expenditure stands at ₹887 Cr, which is 87.4% of the revised project cost.
Remaining budget: ₹128 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Miyagam-Karjan-Dabhoi-Samlaya 96.46 km- Gauge conversion with electrification is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹484.00 Cr, later revised to ₹1015.07 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Miyagam-Karjan-Dabhoi-Samlaya 96.46 km- Gauge conversion with electrification"?
- Miyagam-Karjan-Dabhoi-Samlaya 96.46 km- Gauge conversion with electrification is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Gujarat. Original cost: ₹484 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹484 Cr and has been revised to ₹1015 Cr — a cost overrun of +109.7%. Expenditure to date: ₹887 Cr (87.4% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Miyagam-Karjan-Dabhoi-Samlaya 96.46 km- Gauge conversion wit is under the Ministry of Railways in the Railways sector. Project code: 705458. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Miyagam-Karjan-Dabhoi-Samlaya 96.46 km- Gauge conversion wit is one of several Bihar projects tracked under the Railways sector on the IPM system.