Melaghar-Srimantapur section on NH-08 Spur from Km 23 to Km 34.500 11.5 Km and overlay from Km 20.30 to Km 22.00 1.7 Km Total Length 13.2 Km
Original Cost
₹196 Cr
Baseline estimate
Revised Cost
₹196 Cr
Latest approved cost
Expenditure
₹96 Cr
Spent to date
Utilization
48.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹100 Cr
Budget left
Budget Utilization
48.7%Spent
₹96 Cr
Remaining
₹100 Cr
Total
₹196 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
27/11/2024
Revised Completion
29/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹196 Cr — no cost escalation recorded.
Expenditure stands at ₹96 Cr, which is 48.7% of the revised project cost.
Remaining budget: ₹100 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Melaghar-Srimantapur section on NH-08 Spur from Km 23 to Km 34.500 11.5 Km and overlay from Km 20.30 to Km 22.00 1.7 Km Total Length 13.2 Km is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹196.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Melaghar-Srimantapur section on NH-08 Spur from Km 23 to Km 34.500 11.5 Km and o"?
- Melaghar-Srimantapur section on NH-08 Spur from Km 23 to Km 34.500 11.5 Km and overlay from Km 20.30 to Km 22.00 1.7 Km Total Length 13.2 Km is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tripura. Original cost: ₹196 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹196 Cr has not been significantly revised. Expenditure: ₹96 Cr (48.7% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Melaghar-Srimantapur section on NH-08 Spur from Km 23 to Km is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618411. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Melaghar-Srimantapur section on NH-08 Spur from Km 23 to Km is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.