RailwaysIPM · Central Project#705667

Mathura-Jhansi - 3rd line 273.80 km

Ministry of RailwaysUttar Pradesh
Revised Cost: ₹5961 CrUtilization: 96.0%

Original Cost

₹5961 Cr

Baseline estimate

On budget

Revised Cost

₹5961 Cr

Latest approved cost

Expenditure

₹5725 Cr

Spent to date

Utilization

96.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹236 Cr

Budget left

Budget Utilization

96.0%
0%25%50%75%100%

Spent

₹5725 Cr

Remaining

₹236 Cr

Total

₹5961 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2023

Revised Completion

31/12/2026

Completed

Project Details

Project Code705667
SectorRailways
MinistryMinistry of Railways
StateUttar Pradesh
Data Month2026-08

Financial Summary

Original Cost₹5961 Cr
Revised Cost₹5961 Cr
Expenditure₹5725 Cr
Original End Date31/12/2023
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹5961 Cr — no cost escalation recorded.

Expenditure stands at ₹5725 Cr, which is 96.0% of the revised project cost.

Remaining budget: ₹236 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Mathura-Jhansi - 3rd line 273.80 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹5961.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Mathura-Jhansi - 3rd line 273.80 km"?
Mathura-Jhansi - 3rd line 273.80 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Uttar Pradesh. Original cost: ₹5961 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹5961 Cr has not been significantly revised. Expenditure: ₹5725 Cr (96.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Mathura-Jhansi - 3rd line 273.80 km is under the Ministry of Railways in the Railways sector. Project code: 705667. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Mathura-Jhansi - 3rd line 273.80 km is one of several Bihar projects tracked under the Railways sector on the IPM system.