RailwaysIPM · Central Project +139.7% overrun#705437

Manoharabad-Kothapalli New Rail Line [151 km]

Ministry of RailwaysTelangana
Revised Cost: ₹2781 CrUtilization: 110.5%Overrun: +₹1621 Cr

Original Cost

₹1160 Cr

Baseline estimate

+140% overrun

Revised Cost

₹2781 Cr

Latest approved cost

Expenditure

₹3073 Cr

Spent to date

Utilization

110.5%

Of revised budget

Escalated

Cost Status

+139.7%

+₹1621 Cr increase

Remaining

₹0 Cr

Budget left

Budget Utilization

110.5%
0%25%50%75%100%

Spent

₹3073 Cr

Remaining

₹0 Cr

Total

₹2781 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1160 Cr

Revised Cost

₹2781 Cr

Increase

+₹1621 Cr

Escalation

+139.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2027

Revised Completion

31/12/2027

Completed

Project Details

Project Code705437
SectorRailways
MinistryMinistry of Railways
StateTelangana
Data Month2026-06

Financial Summary

Original Cost₹1160 Cr
Revised Cost₹2781 Cr
Expenditure₹3073 Cr
Original End Date31/03/2027
Revised Date31/12/2027

Project Intelligence

Cost has increased by ₹1621 Cr (139.7%) from the original estimate of ₹1160 Cr.

Expenditure stands at ₹3073 Cr, which is 110.5% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Manoharabad-Kothapalli New Rail Line [151 km] is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1160.00 Cr, later revised to ₹2781.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Manoharabad-Kothapalli New Rail Line [151 km]"?
Manoharabad-Kothapalli New Rail Line [151 km] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Telangana. Original cost: ₹1160 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1160 Cr and has been revised to ₹2781 Cr — a cost overrun of +139.7%. Expenditure to date: ₹3073 Cr (110.5% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Manoharabad-Kothapalli New Rail Line [151 km] is under the Ministry of Railways in the Railways sector. Project code: 705437. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Manoharabad-Kothapalli New Rail Line [151 km] is one of several Bihar projects tracked under the Railways sector on the IPM system.