km. 90.00 of NH-107
Original Cost
₹662 Cr
Baseline estimate
Revised Cost
₹1311 Cr
Latest approved cost
Expenditure
₹933 Cr
Spent to date
Utilization
71.2%
Of revised cost
Cost Overrun
+98.1%
+₹649 Cr
Remaining
₹378 Cr
Budget left
Spent
₹933 Cr
Remaining
₹378 Cr
Total
₹1311 Cr
71.2%
Utilized
Original Cost
₹662 Cr
Revised Cost
₹1311 Cr
Increase
+₹649 Cr
Escalation
+98.1%
Project Approved
Construction / Implementation
Original End Date
2021-12-19
Revised Completion
2026-09-30
Completed
Cost has increased by ₹649 Cr (98.1%) from the original estimate of ₹662 Cr.
Expenditure stands at ₹933 Cr, which is 71.2% of the revised project cost.
Remaining budget: ₹378 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.