Original Cost
₹1061 Cr
Baseline estimate
Revised Cost
₹4417 Cr
Latest approved cost
Expenditure
₹4576 Cr
Spent to date
Utilization
103.6%
Of revised budget
Cost Status
+316.3%
+₹3356 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹4576 Cr
Remaining
₹0 Cr
Total
₹4417 Cr
Original Cost
₹1061 Cr
Revised Cost
₹4417 Cr
Increase
+₹3356 Cr
Escalation
+316.3%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/12/2025
Completed
Cost has increased by ₹3356 Cr (316.3%) from the original estimate of ₹1061 Cr.
Expenditure stands at ₹4576 Cr, which is 103.6% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.