Water ResourcesIPM · Central Project +316.3% overrun#701408

Madhya Ganga canal Phase-II

Department of Water Resources, River Development & GRUttar Pradesh
Revised Cost: ₹4417 CrUtilization: 103.6%Overrun: +₹3356 Cr

Original Cost

₹1061 Cr

Baseline estimate

+316% overrun

Revised Cost

₹4417 Cr

Latest approved cost

Expenditure

₹4576 Cr

Spent to date

Utilization

103.6%

Of revised budget

Escalated

Cost Status

+316.3%

+₹3356 Cr increase

Remaining

₹0 Cr

Budget left

Budget Utilization

103.6%
0%25%50%75%100%

Spent

₹4576 Cr

Remaining

₹0 Cr

Total

₹4417 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1061 Cr

Revised Cost

₹4417 Cr

Increase

+₹3356 Cr

Escalation

+316.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2019

Revised Completion

31/12/2025

Completed

Project Details

Project Code701408
SectorWater Resources
MinistryDepartment of Water Resources, River Development & GR
StateUttar Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1061 Cr
Revised Cost₹4417 Cr
Expenditure₹4576 Cr
Original End Date31/12/2019
Revised Date31/12/2025

Project Intelligence

Cost has increased by ₹3356 Cr (316.3%) from the original estimate of ₹1061 Cr.

Expenditure stands at ₹4576 Cr, which is 103.6% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.

Madhya Ganga canal Phase-II is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹1061.00 Cr, later revised to ₹4417.21 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Madhya Ganga canal Phase-II"?
Madhya Ganga canal Phase-II is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Uttar Pradesh. Original cost: ₹1061 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1061 Cr and has been revised to ₹4417 Cr — a cost overrun of +316.3%. Expenditure to date: ₹4576 Cr (103.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Madhya Ganga canal Phase-II is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 701408. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Madhya Ganga canal Phase-II is one of several Bihar projects tracked under the Water Resources sector on the IPM system.