Original Cost
₹202 Cr
Baseline estimate
Revised Cost
₹202 Cr
Latest approved cost
Expenditure
₹65 Cr
Spent to date
Utilization
32.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹137 Cr
Budget left
Spent
₹65 Cr
Remaining
₹137 Cr
Total
₹202 Cr
Project Approved
Construction / Implementation
Original End Date
08/02/2026
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹202 Cr — no cost escalation recorded.
Expenditure stands at ₹65 Cr, which is 32.1% of the revised project cost.
Remaining budget: ₹137 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.