Laying of Natural Gas Pipeline from Hazaribagh to Ranchi [HRPL]
Original Cost
₹202 Cr
Baseline estimate
Revised Cost
₹202 Cr
Latest approved cost
Expenditure
₹67 Cr
Spent to date
Utilization
33.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹135 Cr
Budget left
Budget Utilization
33.0%Spent
₹67 Cr
Remaining
₹135 Cr
Total
₹202 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
08/02/2026
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹202 Cr — no cost escalation recorded.
Expenditure stands at ₹67 Cr, which is 33.0% of the revised project cost.
Remaining budget: ₹135 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.
Laying of Natural Gas Pipeline from Hazaribagh to Ranchi [HRPL] is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹202.00 Cr, later revised to ₹202.07 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Laying of Natural Gas Pipeline from Hazaribagh to Ranchi [HRPL]"?
- Laying of Natural Gas Pipeline from Hazaribagh to Ranchi [HRPL] is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Jharkhand. Original cost: ₹202 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹202 Cr has not been significantly revised. Expenditure: ₹67 Cr (33.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Laying of Natural Gas Pipeline from Hazaribagh to Ranchi [HR is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 709785. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Laying of Natural Gas Pipeline from Hazaribagh to Ranchi [HR is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.