Original Cost
₹974 Cr
Baseline estimate
Revised Cost
₹2775 Cr
Latest approved cost
Expenditure
₹1070 Cr
Spent to date
Utilization
38.6%
Of revised budget
Cost Status
+184.9%
+₹1801 Cr increase
Remaining
₹1705 Cr
Budget left
Spent
₹1070 Cr
Remaining
₹1705 Cr
Total
₹2775 Cr
Original Cost
₹974 Cr
Revised Cost
₹2775 Cr
Increase
+₹1801 Cr
Escalation
+184.9%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/12/2023
Completed
Cost has increased by ₹1801 Cr (184.9%) from the original estimate of ₹974 Cr.
Expenditure stands at ₹1070 Cr, which is 38.6% of the revised project cost.
Remaining budget: ₹1705 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.