RailwaysIPM · Central Project +43.2% overrun#705512

Kottavalasa-Koraput 189.278 km

Ministry of RailwaysOdisha
Revised Cost: ₹3580 CrUtilization: 65.9%Overrun: +₹1080 Cr

Original Cost

₹2500 Cr

Baseline estimate

+43% overrun

Revised Cost

₹3580 Cr

Latest approved cost

Expenditure

₹2359 Cr

Spent to date

Utilization

65.9%

Of revised budget

Escalated

Cost Status

+43.2%

+₹1080 Cr increase

Remaining

₹1221 Cr

Budget left

Budget Utilization

65.9%
0%25%50%75%100%

Spent

₹2359 Cr

Remaining

₹1221 Cr

Total

₹3580 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2500 Cr

Revised Cost

₹3580 Cr

Increase

+₹1080 Cr

Escalation

+43.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2022

Revised Completion

31/03/2028

Completed

Project Details

Project Code705512
SectorRailways
MinistryMinistry of Railways
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹2500 Cr
Revised Cost₹3580 Cr
Expenditure₹2359 Cr
Original End Date31/03/2022
Revised Date31/03/2028

Project Intelligence

Cost has increased by ₹1080 Cr (43.2%) from the original estimate of ₹2500 Cr.

Expenditure stands at ₹2359 Cr, which is 65.9% of the revised project cost.

Remaining budget: ₹1221 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Kottavalasa-Koraput 189.278 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹2500.00 Cr, later revised to ₹3580.41 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Kottavalasa-Koraput 189.278 km"?
Kottavalasa-Koraput 189.278 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Odisha. Original cost: ₹2500 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2500 Cr and has been revised to ₹3580 Cr — a cost overrun of +43.2%. Expenditure to date: ₹2359 Cr (65.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Kottavalasa-Koraput 189.278 km is under the Ministry of Railways in the Railways sector. Project code: 705512. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kottavalasa-Koraput 189.278 km is one of several Bihar projects tracked under the Railways sector on the IPM system.