Kottavalasa-Koraput 189.278 km
Original Cost
₹2500 Cr
Baseline estimate
Revised Cost
₹3580 Cr
Latest approved cost
Expenditure
₹2359 Cr
Spent to date
Utilization
65.9%
Of revised budget
Cost Status
+43.2%
+₹1080 Cr increase
Remaining
₹1221 Cr
Budget left
Budget Utilization
65.9%Spent
₹2359 Cr
Remaining
₹1221 Cr
Total
₹3580 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2500 Cr
Revised Cost
₹3580 Cr
Increase
+₹1080 Cr
Escalation
+43.2%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2022
Revised Completion
31/03/2028
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹1080 Cr (43.2%) from the original estimate of ₹2500 Cr.
Expenditure stands at ₹2359 Cr, which is 65.9% of the revised project cost.
Remaining budget: ₹1221 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Kottavalasa-Koraput 189.278 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹2500.00 Cr, later revised to ₹3580.41 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Kottavalasa-Koraput 189.278 km"?
- Kottavalasa-Koraput 189.278 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Odisha. Original cost: ₹2500 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2500 Cr and has been revised to ₹3580 Cr — a cost overrun of +43.2%. Expenditure to date: ₹2359 Cr (65.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Kottavalasa-Koraput 189.278 km is under the Ministry of Railways in the Railways sector. Project code: 705512. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kottavalasa-Koraput 189.278 km is one of several Bihar projects tracked under the Railways sector on the IPM system.