Original Cost
₹2501 Cr
Baseline estimate
Revised Cost
₹2501 Cr
Latest approved cost
Expenditure
₹1418 Cr
Spent to date
Utilization
56.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1083 Cr
Budget left
Spent
₹1418 Cr
Remaining
₹1083 Cr
Total
₹2501 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2028
Revised Completion
31/03/2028
Completed
Project is within original budget of ₹2501 Cr — no cost escalation recorded.
Expenditure stands at ₹1418 Cr, which is 56.7% of the revised project cost.
Remaining budget: ₹1083 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.