Roads & HighwaysIPM · Central Project +26.1% overrun#618833

Kodinar - Veraval Package VI from km. 221.610 to km. 263.00 of NH-8E & km. 120.900 to km. 121.150 of NH-8D

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹1127 CrUtilization: 64.8%Overrun: +₹233 Cr

Original Cost

₹894 Cr

Baseline estimate

+26% overrun

Revised Cost

₹1127 Cr

Latest approved cost

Expenditure

₹730 Cr

Spent to date

Utilization

64.8%

Of revised budget

Escalated

Cost Status

+26.1%

+₹233 Cr increase

Remaining

₹397 Cr

Budget left

Budget Utilization

64.8%
0%25%50%75%100%

Spent

₹730 Cr

Remaining

₹397 Cr

Total

₹1127 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹894 Cr

Revised Cost

₹1127 Cr

Increase

+₹233 Cr

Escalation

+26.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/07/2020

Revised Completion

10/07/2026

Completed

Project Details

Project Code618833
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-06

Financial Summary

Original Cost₹894 Cr
Revised Cost₹1127 Cr
Expenditure₹730 Cr
Original End Date30/07/2020
Revised Date10/07/2026

Project Intelligence

Cost has increased by ₹233 Cr (26.1%) from the original estimate of ₹894 Cr.

Expenditure stands at ₹730 Cr, which is 64.8% of the revised project cost.

Remaining budget: ₹397 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Kodinar - Veraval Package VI from km. 221.610 to km. 263.00 of NH-8E & km. 120.900 to km. 121.150 of NH-8D is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹894.00 Cr, later revised to ₹1127.42 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Kodinar - Veraval Package VI from km. 221.610 to km. 263.00 of NH-8E & km. 120.9"?
Kodinar - Veraval Package VI from km. 221.610 to km. 263.00 of NH-8E & km. 120.900 to km. 121.150 of NH-8D is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹894 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹894 Cr and has been revised to ₹1127 Cr — a cost overrun of +26.1%. Expenditure to date: ₹730 Cr (64.8% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Kodinar - Veraval Package VI from km. 221.610 to km. 263.00 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618833. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kodinar - Veraval Package VI from km. 221.610 to km. 263.00 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.