Original Cost
₹2915 Cr
Baseline estimate
Revised Cost
₹5909 Cr
Latest approved cost
Expenditure
₹4799 Cr
Spent to date
Utilization
81.2%
Of revised budget
Cost Status
+102.7%
+₹2994 Cr increase
Remaining
₹1110 Cr
Budget left
Spent
₹4799 Cr
Remaining
₹1110 Cr
Total
₹5909 Cr
Original Cost
₹2915 Cr
Revised Cost
₹5909 Cr
Increase
+₹2994 Cr
Escalation
+102.7%
Project Approved
Construction / Implementation
Original End Date
31/12/2012
Revised Completion
30/09/2026
Completed
Cost has increased by ₹2994 Cr (102.7%) from the original estimate of ₹2915 Cr.
Expenditure stands at ₹4799 Cr, which is 81.2% of the revised project cost.
Remaining budget: ₹1110 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.