Oil & GasIPM · Central Project +102.7% overrun#701228

Kochi - Koottanad - Bangalore - Mangalore Pipeline Phase-II

Ministry of Petroleum & Natural GasTamil Nadu
Revised Cost: ₹5909 CrUtilization: 82.9%Overrun: +₹2994 Cr

Original Cost

₹2915 Cr

Baseline estimate

+103% overrun

Revised Cost

₹5909 Cr

Latest approved cost

Expenditure

₹4898 Cr

Spent to date

Utilization

82.9%

Of revised budget

Escalated

Cost Status

+102.7%

+₹2994 Cr increase

Remaining

₹1011 Cr

Budget left

Budget Utilization

82.9%
0%25%50%75%100%

Spent

₹4898 Cr

Remaining

₹1011 Cr

Total

₹5909 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2915 Cr

Revised Cost

₹5909 Cr

Increase

+₹2994 Cr

Escalation

+102.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2012

Revised Completion

30/09/2026

Completed

Project Details

Project Code701228
SectorOil & Gas
MinistryMinistry of Petroleum & Natural Gas
StateTamil Nadu
Data Month2026-08

Financial Summary

Original Cost₹2915 Cr
Revised Cost₹5909 Cr
Expenditure₹4898 Cr
Original End Date31/12/2012
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹2994 Cr (102.7%) from the original estimate of ₹2915 Cr.

Expenditure stands at ₹4898 Cr, which is 82.9% of the revised project cost.

Remaining budget: ₹1011 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.

Kochi - Koottanad - Bangalore - Mangalore Pipeline Phase-II is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹2915.00 Cr, later revised to ₹5909.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Kochi - Koottanad - Bangalore - Mangalore Pipeline Phase-II"?
Kochi - Koottanad - Bangalore - Mangalore Pipeline Phase-II is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Tamil Nadu. Original cost: ₹2915 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2915 Cr and has been revised to ₹5909 Cr — a cost overrun of +102.7%. Expenditure to date: ₹4898 Cr (82.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Kochi - Koottanad - Bangalore - Mangalore Pipeline Phase-II is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 701228. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kochi - Koottanad - Bangalore - Mangalore Pipeline Phase-II is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.