Khurda Road - Balangir Electrification of Railway Track Project
Original Cost
₹268 Cr
Baseline estimate
Revised Cost
₹268 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹268 Cr
Budget left
Budget Utilization
0.0%Spent
₹0 Cr
Remaining
₹268 Cr
Total
₹268 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2021
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹268 Cr — no cost escalation recorded.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹268 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Khurda Road - Balangir Electrification of Railway Track Project is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹268.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Khurda Road - Balangir Electrification of Railway Track Project"?
- Khurda Road - Balangir Electrification of Railway Track Project is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Odisha. Original cost: ₹268 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹268 Cr has not been significantly revised. Expenditure: ₹0 Cr (N/A% of cost). Data as of 2026-06.
- QWhich ministry is responsible for this project?
- Khurda Road - Balangir Electrification of Railway Track Proj is under the Ministry of Railways in the Railways sector. Project code: 706898. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Khurda Road - Balangir Electrification of Railway Track Proj is one of several Bihar projects tracked under the Railways sector on the IPM system.