Original Cost
₹3055 Cr
Baseline estimate
Revised Cost
₹3798 Cr
Latest approved cost
Expenditure
₹2730 Cr
Spent to date
Utilization
71.9%
Of revised budget
Cost Status
+24.3%
+₹743 Cr increase
Remaining
₹1068 Cr
Budget left
Spent
₹2730 Cr
Remaining
₹1068 Cr
Total
₹3798 Cr
Original Cost
₹3055 Cr
Revised Cost
₹3798 Cr
Increase
+₹743 Cr
Escalation
+24.3%
Project Approved
Construction / Implementation
Original End Date
30/09/2018
Revised Completion
31/12/2026
Completed
Cost has increased by ₹743 Cr (24.3%) from the original estimate of ₹3055 Cr.
Expenditure stands at ₹2730 Cr, which is 71.9% of the revised project cost.
Remaining budget: ₹1068 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.