Original Cost
₹830 Cr
Baseline estimate
Revised Cost
₹1227 Cr
Latest approved cost
Expenditure
₹519 Cr
Spent to date
Utilization
42.3%
Of revised budget
Cost Status
+47.8%
+₹397 Cr increase
Remaining
₹708 Cr
Budget left
Spent
₹519 Cr
Remaining
₹708 Cr
Total
₹1227 Cr
Original Cost
₹830 Cr
Revised Cost
₹1227 Cr
Increase
+₹397 Cr
Escalation
+47.8%
Project Approved
Construction / Implementation
Original End Date
26/09/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹397 Cr (47.8%) from the original estimate of ₹830 Cr.
Expenditure stands at ₹519 Cr, which is 42.3% of the revised project cost.
Remaining budget: ₹708 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.