Original Cost
₹460 Cr
Baseline estimate
Revised Cost
₹727 Cr
Latest approved cost
Expenditure
₹619 Cr
Spent to date
Utilization
85.1%
Of revised budget
Cost Status
+58.1%
+₹267 Cr increase
Remaining
₹108 Cr
Budget left
Spent
₹619 Cr
Remaining
₹108 Cr
Total
₹727 Cr
Original Cost
₹460 Cr
Revised Cost
₹727 Cr
Increase
+₹267 Cr
Escalation
+58.1%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
30/06/2026
Completed
Cost has increased by ₹267 Cr (58.1%) from the original estimate of ₹460 Cr.
Expenditure stands at ₹619 Cr, which is 85.1% of the revised project cost.
Remaining budget: ₹108 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.