Katni - Grade separator / bypass 21.50 km
Original Cost
₹1248 Cr
Baseline estimate
Revised Cost
₹2300 Cr
Latest approved cost
Expenditure
₹1839 Cr
Spent to date
Utilization
80.0%
Of revised budget
Cost Status
+84.3%
+₹1052 Cr increase
Remaining
₹461 Cr
Budget left
Budget Utilization
80.0%Spent
₹1839 Cr
Remaining
₹461 Cr
Total
₹2300 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1248 Cr
Revised Cost
₹2300 Cr
Increase
+₹1052 Cr
Escalation
+84.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/09/2024
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹1052 Cr (84.3%) from the original estimate of ₹1248 Cr.
Expenditure stands at ₹1839 Cr, which is 80.0% of the revised project cost.
Remaining budget: ₹461 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Katni - Grade separator / bypass 21.50 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1248.00 Cr, later revised to ₹2300.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Katni - Grade separator / bypass 21.50 km"?
- Katni - Grade separator / bypass 21.50 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Madhya Pradesh. Original cost: ₹1248 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1248 Cr and has been revised to ₹2300 Cr — a cost overrun of +84.3%. Expenditure to date: ₹1839 Cr (80.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Katni - Grade separator / bypass 21.50 km is under the Ministry of Railways in the Railways sector. Project code: 705661. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Katni - Grade separator / bypass 21.50 km is one of several Bihar projects tracked under the Railways sector on the IPM system.