Katihar-Kumedpur & Katihar-Mukuria 64.5 km Umbrella work PB57/2019-20/NR
Original Cost
₹943 Cr
Baseline estimate
Revised Cost
₹1961 Cr
Latest approved cost
Expenditure
₹953 Cr
Spent to date
Utilization
48.6%
Of revised budget
Cost Status
+108.0%
+₹1018 Cr increase
Remaining
₹1008 Cr
Budget left
Budget Utilization
48.6%Spent
₹953 Cr
Remaining
₹1008 Cr
Total
₹1961 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹943 Cr
Revised Cost
₹1961 Cr
Increase
+₹1018 Cr
Escalation
+108.0%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/08/2027
Revised Completion
28/02/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹1018 Cr (108.0%) from the original estimate of ₹943 Cr.
Expenditure stands at ₹953 Cr, which is 48.6% of the revised project cost.
Remaining budget: ₹1008 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Katihar-Kumedpur & Katihar-Mukuria 64.5 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹943.00 Cr, later revised to ₹1961.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Katihar-Kumedpur & Katihar-Mukuria 64.5 km Umbrella work PB57/2019-20/NR"?
- Katihar-Kumedpur & Katihar-Mukuria 64.5 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: West Bengal. Original cost: ₹943 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹943 Cr and has been revised to ₹1961 Cr — a cost overrun of +108%. Expenditure to date: ₹953 Cr (48.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Katihar-Kumedpur & Katihar-Mukuria 64.5 km Umbrella work PB5 is under the Ministry of Railways in the Railways sector. Project code: 617245. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Katihar-Kumedpur & Katihar-Mukuria 64.5 km Umbrella work PB5 is one of several Bihar projects tracked under the Railways sector on the IPM system.