Original Cost
₹680 Cr
Baseline estimate
Revised Cost
₹701 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
+3.2%
+₹21 Cr increase
Remaining
₹701 Cr
Budget left
Spent
₹0 Cr
Remaining
₹701 Cr
Total
₹701 Cr
Original Cost
₹680 Cr
Revised Cost
₹701 Cr
Increase
+₹21 Cr
Escalation
+3.2%
Project Approved
Construction / Implementation
Original End Date
14/04/2021
Revised Completion
14/04/2021
Completed
Cost has increased by ₹21 Cr (3.2%) from the original estimate of ₹680 Cr.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹701 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.