Revised Cost: ₹2021 CrUtilization: 65.1%Overrun: +₹903 Cr

Original Cost

₹1118 Cr

Baseline estimate

+81% overrun

Revised Cost

₹2021 Cr

Latest approved cost

Expenditure

₹1315 Cr

Spent to date

Utilization

65.1%

Of revised budget

Escalated

Cost Status

+80.7%

+₹903 Cr increase

Remaining

₹705 Cr

Budget left

Budget Utilization

65.1%
0%25%50%75%100%

Spent

₹1315 Cr

Remaining

₹705 Cr

Total

₹2021 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1118 Cr

Revised Cost

₹2021 Cr

Increase

+₹903 Cr

Escalation

+80.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

12/11/2019

Revised Completion

30/11/2025

Completed

Project Details

Project Code617948
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹1118 Cr
Revised Cost₹2021 Cr
Expenditure₹1315 Cr
Original End Date12/11/2019
Revised Date30/11/2025

Project Intelligence

Cost has increased by ₹903 Cr (80.7%) from the original estimate of ₹1118 Cr.

Expenditure stands at ₹1315 Cr, which is 65.1% of the revised project cost.

Remaining budget: ₹705 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Kante - Wakad section of NH-66 4L PS from Km.281/300 to 332/200 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1118.00 Cr, later revised to ₹2020.56 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Kante - Wakad section of NH-66 4L PS from Km.281/300 to 332/200"?
Kante - Wakad section of NH-66 4L PS from Km.281/300 to 332/200 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹1118 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1118 Cr and has been revised to ₹2021 Cr — a cost overrun of +80.7%. Expenditure to date: ₹1315 Cr (65.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Kante - Wakad section of NH-66 4L PS from Km.281/300 to 332 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617948. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kante - Wakad section of NH-66 4L PS from Km.281/300 to 332 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.