RailwaysIPM · Central Project +26.4% overrun#705492

Kadur-Chickmagalur-Sakleshpur 93 km

Ministry of RailwaysKarnataka
Revised Cost: ₹1043 CrUtilization: 76.9%Overrun: +₹218 Cr

Original Cost

₹825 Cr

Baseline estimate

+26% overrun

Revised Cost

₹1043 Cr

Latest approved cost

Expenditure

₹802 Cr

Spent to date

Utilization

76.9%

Of revised budget

Escalated

Cost Status

+26.4%

+₹218 Cr increase

Remaining

₹241 Cr

Budget left

Budget Utilization

76.9%
0%25%50%75%100%

Spent

₹802 Cr

Remaining

₹241 Cr

Total

₹1043 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹825 Cr

Revised Cost

₹1043 Cr

Increase

+₹218 Cr

Escalation

+26.4%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/06/2025

Revised Completion

31/12/2025

Completed

Project Details

Project Code705492
SectorRailways
MinistryMinistry of Railways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹825 Cr
Revised Cost₹1043 Cr
Expenditure₹802 Cr
Original End Date30/06/2025
Revised Date31/12/2025

Project Intelligence

Cost has increased by ₹218 Cr (26.4%) from the original estimate of ₹825 Cr.

Expenditure stands at ₹802 Cr, which is 76.9% of the revised project cost.

Remaining budget: ₹241 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Kadur-Chickmagalur-Sakleshpur 93 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹825.00 Cr, later revised to ₹1043.15 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Kadur-Chickmagalur-Sakleshpur 93 km"?
Kadur-Chickmagalur-Sakleshpur 93 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Karnataka. Original cost: ₹825 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹825 Cr and has been revised to ₹1043 Cr — a cost overrun of +26.4%. Expenditure to date: ₹802 Cr (76.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Kadur-Chickmagalur-Sakleshpur 93 km is under the Ministry of Railways in the Railways sector. Project code: 705492. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kadur-Chickmagalur-Sakleshpur 93 km is one of several Bihar projects tracked under the Railways sector on the IPM system.