Line project
Original Cost
₹402 Cr
Baseline estimate
Revised Cost
₹486 Cr
Latest approved cost
Expenditure
₹369 Cr
Spent to date
Utilization
76.0%
Of revised cost
Cost Overrun
+20.9%
+₹84 Cr
Remaining
₹117 Cr
Budget left
Spent
₹369 Cr
Remaining
₹117 Cr
Total
₹486 Cr
76.0%
Utilized
Original Cost
₹402 Cr
Revised Cost
₹486 Cr
Increase
+₹84 Cr
Escalation
+20.9%
Project Approved
Construction / Implementation
Original End Date
2022-03-31
Revised Completion
2026-12-31
Completed
Cost has increased by ₹84 Cr (20.9%) from the original estimate of ₹402 Cr.
Expenditure stands at ₹369 Cr, which is 76.0% of the revised project cost.
Remaining budget: ₹117 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.