Jarapaada-Budhapank with flyover at Talcher Road - 3rd & 4th line 47 44 km
Original Cost
₹1000 Cr
Baseline estimate
Revised Cost
₹929 Cr
Latest approved cost
Expenditure
₹759 Cr
Spent to date
Utilization
81.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹170 Cr
Budget left
Budget Utilization
81.7%Spent
₹759 Cr
Remaining
₹170 Cr
Total
₹929 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
13/11/2018
Revised Completion
31/03/2028
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1000 Cr — no cost escalation recorded.
Expenditure stands at ₹759 Cr, which is 81.7% of the revised project cost.
Remaining budget: ₹170 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Jarapaada-Budhapank with flyover at Talcher Road - 3rd & 4th line 47 44 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1000.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Jarapaada-Budhapank with flyover at Talcher Road - 3rd & 4th line 47 44 km"?
- Jarapaada-Budhapank with flyover at Talcher Road - 3rd & 4th line 47 44 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Odisha. Original cost: ₹1000 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1000 Cr and has been revised to ₹929 Cr — a cost overrun of -7.1%. Expenditure to date: ₹759 Cr (81.7% of revised cost). Data as of 2026-07.
- QWhich ministry is responsible for this project?
- Jarapaada-Budhapank with flyover at Talcher Road - 3rd & 4th is under the Ministry of Railways in the Railways sector. Project code: 705514. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Jarapaada-Budhapank with flyover at Talcher Road - 3rd & 4th is one of several Bihar projects tracked under the Railways sector on the IPM system.