Original Cost
₹357 Cr
Baseline estimate
Revised Cost
₹979 Cr
Latest approved cost
Expenditure
₹579 Cr
Spent to date
Utilization
59.2%
Of revised budget
Cost Status
+174.2%
+₹622 Cr increase
Remaining
₹400 Cr
Budget left
Spent
₹579 Cr
Remaining
₹400 Cr
Total
₹979 Cr
Original Cost
₹357 Cr
Revised Cost
₹979 Cr
Increase
+₹622 Cr
Escalation
+174.2%
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
31/03/2025
Completed
Cost has increased by ₹622 Cr (174.2%) from the original estimate of ₹357 Cr.
Expenditure stands at ₹579 Cr, which is 59.2% of the revised project cost.
Remaining budget: ₹400 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.