Water ResourcesIPM · Central Project#613787

Jamrani Dam Multipurpose Project

Department of Water Resources, River Development & GRUttarakhand
Revised Cost: ₹2584 CrUtilization: 53.4%

Original Cost

₹2584 Cr

Baseline estimate

On budget

Revised Cost

₹2584 Cr

Latest approved cost

Expenditure

₹1380 Cr

Spent to date

Utilization

53.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1204 Cr

Budget left

Budget Utilization

53.4%
0%25%50%75%100%

Spent

₹1380 Cr

Remaining

₹1204 Cr

Total

₹2584 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

28/06/2029

Revised Completion

Completed

Project Details

Project Code613787
SectorWater Resources
MinistryDepartment of Water Resources, River Development & GR
StateUttarakhand
Data Month2026-08

Financial Summary

Original Cost₹2584 Cr
Revised Cost₹2584 Cr
Expenditure₹1380 Cr
Original End Date28/06/2029
Revised DateN/A

Project Intelligence

Project is within original budget of ₹2584 Cr — no cost escalation recorded.

Expenditure stands at ₹1380 Cr, which is 53.4% of the revised project cost.

Remaining budget: ₹1204 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.

Jamrani Dam Multipurpose Project is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹2584.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Jamrani Dam Multipurpose Project"?
Jamrani Dam Multipurpose Project is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Uttarakhand. Original cost: ₹2584 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹2584 Cr has not been significantly revised. Expenditure: ₹1380 Cr (53.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Jamrani Dam Multipurpose Project is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 613787. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Jamrani Dam Multipurpose Project is one of several Bihar projects tracked under the Water Resources sector on the IPM system.