Roads & HighwaysIPM · Central Project#618936

Jagadhari - Tajewala from Km -0.175 to 32.337 km of NH-344

Ministry of Road Transport & HighwaysHaryana
Revised Cost: ₹919 CrUtilization: 78.9%

Original Cost

₹1270 Cr

Baseline estimate

On budget

Revised Cost

₹919 Cr

Latest approved cost

Expenditure

₹725 Cr

Spent to date

Utilization

78.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹194 Cr

Budget left

Budget Utilization

78.9%
0%25%50%75%100%

Spent

₹725 Cr

Remaining

₹194 Cr

Total

₹919 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/02/2025

Revised Completion

31/03/2027

Completed

Project Details

Project Code618936
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateHaryana
Data Month2026-08

Financial Summary

Original Cost₹1270 Cr
Revised Cost₹919 Cr
Expenditure₹725 Cr
Original End Date06/02/2025
Revised Date31/03/2027

Project Intelligence

Project is within original budget of ₹1270 Cr — no cost escalation recorded.

Expenditure stands at ₹725 Cr, which is 78.9% of the revised project cost.

Remaining budget: ₹194 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Jagadhari - Tajewala from Km -0.175 to 32.337 km of NH-344 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1270.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Jagadhari - Tajewala from Km -0.175 to 32.337 km of NH-344"?
Jagadhari - Tajewala from Km -0.175 to 32.337 km of NH-344 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Haryana. Original cost: ₹1270 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1270 Cr and has been revised to ₹919 Cr — a cost overrun of -27.6%. Expenditure to date: ₹725 Cr (78.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Jagadhari - Tajewala from Km -0.175 to 32.337 km of NH-344 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618936. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Jagadhari - Tajewala from Km -0.175 to 32.337 km of NH-344 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.