Original Cost
₹1270 Cr
Baseline estimate
Revised Cost
₹919 Cr
Latest approved cost
Expenditure
₹680 Cr
Spent to date
Utilization
73.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹240 Cr
Budget left
Spent
₹680 Cr
Remaining
₹240 Cr
Total
₹919 Cr
Project Approved
Construction / Implementation
Original End Date
06/02/2025
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹1270 Cr — no cost escalation recorded.
Expenditure stands at ₹680 Cr, which is 73.9% of the revised project cost.
Remaining budget: ₹240 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.