Original Cost
₹8201 Cr
Baseline estimate
Revised Cost
₹14.7K Cr
Latest approved cost
Expenditure
₹4785 Cr
Spent to date
Utilization
32.5%
Of revised budget
Cost Status
+79.6%
+₹6529 Cr increase
Remaining
₹9945 Cr
Budget left
Spent
₹4785 Cr
Remaining
₹9945 Cr
Total
₹14.7K Cr
Original Cost
₹8201 Cr
Revised Cost
₹14.7K Cr
Increase
+₹6529 Cr
Escalation
+79.6%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/12/2025
Completed
Mega infrastructure project worth ₹14.7K Cr — among the largest central projects in Telangana.
Cost has increased by ₹6529 Cr (79.6%) from the original estimate of ₹8201 Cr.
Expenditure stands at ₹4785 Cr, which is 32.5% of the revised project cost.
Remaining budget: ₹9945 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.