Original Cost
₹567 Cr
Baseline estimate
Revised Cost
₹2990 Cr
Latest approved cost
Expenditure
₹2776 Cr
Spent to date
Utilization
92.8%
Of revised budget
Cost Status
+427.3%
+₹2423 Cr increase
Remaining
₹214 Cr
Budget left
Spent
₹2776 Cr
Remaining
₹214 Cr
Total
₹2990 Cr
Original Cost
₹567 Cr
Revised Cost
₹2990 Cr
Increase
+₹2423 Cr
Escalation
+427.3%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
30/06/2026
Completed
Cost has increased by ₹2423 Cr (427.3%) from the original estimate of ₹567 Cr.
Expenditure stands at ₹2776 Cr, which is 92.8% of the revised project cost.
Remaining budget: ₹214 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.