Water ResourcesIPM · Central Project +427.3% overrun#603945

Integrated Anandpur Barrage Project

Department of Water Resources, River Development & GROdisha
Revised Cost: ₹2990 CrUtilization: 94.9%Overrun: +₹2423 Cr

Original Cost

₹567 Cr

Baseline estimate

+427% overrun

Revised Cost

₹2990 Cr

Latest approved cost

Expenditure

₹2837 Cr

Spent to date

Utilization

94.9%

Of revised budget

Escalated

Cost Status

+427.3%

+₹2423 Cr increase

Remaining

₹154 Cr

Budget left

Budget Utilization

94.9%
0%25%50%75%100%

Spent

₹2837 Cr

Remaining

₹154 Cr

Total

₹2990 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹567 Cr

Revised Cost

₹2990 Cr

Increase

+₹2423 Cr

Escalation

+427.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2019

Revised Completion

30/06/2028

Completed

Project Details

Project Code603945
SectorWater Resources
MinistryDepartment of Water Resources, River Development & GR
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹567 Cr
Revised Cost₹2990 Cr
Expenditure₹2837 Cr
Original End Date31/12/2019
Revised Date30/06/2028

Project Intelligence

Cost has increased by ₹2423 Cr (427.3%) from the original estimate of ₹567 Cr.

Expenditure stands at ₹2837 Cr, which is 94.9% of the revised project cost.

Remaining budget: ₹154 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.

Integrated Anandpur Barrage Project is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹567.00 Cr, later revised to ₹2990.05 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Integrated Anandpur Barrage Project"?
Integrated Anandpur Barrage Project is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Odisha. Original cost: ₹567 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹567 Cr and has been revised to ₹2990 Cr — a cost overrun of +427.3%. Expenditure to date: ₹2837 Cr (94.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Integrated Anandpur Barrage Project is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 603945. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Integrated Anandpur Barrage Project is one of several Bihar projects tracked under the Water Resources sector on the IPM system.