Original Cost
₹1175 Cr
Baseline estimate
Revised Cost
₹217 Cr
Latest approved cost
Expenditure
₹14 Cr
Spent to date
Utilization
6.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹203 Cr
Budget left
Spent
₹14 Cr
Remaining
₹203 Cr
Total
₹217 Cr
Project Approved
Construction / Implementation
Original End Date
14/02/2013
Revised Completion
31/05/2026
Completed
Project is within original budget of ₹1175 Cr — no cost escalation recorded.
Expenditure stands at ₹14 Cr, which is 6.5% of the revised project cost.
Remaining budget: ₹203 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.