Original Cost
₹7474 Cr
Baseline estimate
Revised Cost
₹7474 Cr
Latest approved cost
Expenditure
₹2618 Cr
Spent to date
Utilization
35.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹4856 Cr
Budget left
Spent
₹2618 Cr
Remaining
₹4856 Cr
Total
₹7474 Cr
Project Approved
Construction / Implementation
Original End Date
30/09/2030
Revised Completion
30/09/2030
Completed
Project is within original budget of ₹7474 Cr — no cost escalation recorded.
Expenditure stands at ₹2618 Cr, which is 35.0% of the revised project cost.
Remaining budget: ₹4856 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.