Original Cost
₹1331 Cr
Baseline estimate
Revised Cost
₹5940 Cr
Latest approved cost
Expenditure
₹4491 Cr
Spent to date
Utilization
75.6%
Of revised budget
Cost Status
+346.3%
+₹4609 Cr increase
Remaining
₹1449 Cr
Budget left
Spent
₹4491 Cr
Remaining
₹1449 Cr
Total
₹5940 Cr
Original Cost
₹1331 Cr
Revised Cost
₹5940 Cr
Increase
+₹4609 Cr
Escalation
+346.3%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/12/2026
Completed
Cost has increased by ₹4609 Cr (346.3%) from the original estimate of ₹1331 Cr.
Expenditure stands at ₹4491 Cr, which is 75.6% of the revised project cost.
Remaining budget: ₹1449 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.