Improvement/Up-gradation of existing 2-Lane Road to 4-Lane Divided Highway from Daili to Kuraopokpi section of Imphal-Kohima road NH-02 Design Chainage from Km 274610 to Km 287000 in the state of Manipur on EPC mode Pkg-4B
Original Cost
₹269 Cr
Baseline estimate
Revised Cost
₹269 Cr
Latest approved cost
Expenditure
₹210 Cr
Spent to date
Utilization
78.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹59 Cr
Budget left
Budget Utilization
78.2%Spent
₹210 Cr
Remaining
₹59 Cr
Total
₹269 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
05/06/2026
Revised Completion
24/01/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹269 Cr — no cost escalation recorded.
Expenditure stands at ₹210 Cr, which is 78.2% of the revised project cost.
Remaining budget: ₹59 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Improvement/Up-gradation of existing 2-Lane Road to 4-Lane Divided Highway from Daili to Kuraopokpi section of Imphal-Kohima road NH-02 Design Chainage from Km 274610 to Km 287000 in the state of Manipur on EPC mode Pkg-4B is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹269.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Improvement/Up-gradation of existing 2-Lane Road to 4-Lane Divided Highway from "?
- Improvement/Up-gradation of existing 2-Lane Road to 4-Lane Divided Highway from Daili to Kuraopokpi section of Imphal-Kohima road NH-02 Design Chainage from Km 274610 to Km 287000 in the state of Manipur on EPC mode Pkg-4B is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Manipur. Original cost: ₹269 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹269 Cr has not been significantly revised. Expenditure: ₹210 Cr (78.2% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Improvement/Up-gradation of existing 2-Lane Road to 4-Lane D is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618299. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Improvement/Up-gradation of existing 2-Lane Road to 4-Lane D is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.