Original Cost
₹231 Cr
Baseline estimate
Revised Cost
₹203 Cr
Latest approved cost
Expenditure
₹15 Cr
Spent to date
Utilization
7.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹188 Cr
Budget left
Spent
₹15 Cr
Remaining
₹188 Cr
Total
₹203 Cr
Project Approved
Construction / Implementation
Original End Date
30/06/2026
Revised Completion
30/09/2027
Completed
Project is within original budget of ₹231 Cr — no cost escalation recorded.
Expenditure stands at ₹15 Cr, which is 7.5% of the revised project cost.
Remaining budget: ₹188 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.