of NH 131 A Total length 23.945 Km under EPC mode in the state of Bihar
Original Cost
₹353 Cr
Baseline estimate
Revised Cost
₹353 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹353 Cr
Budget left
Spent
₹0 Cr
Remaining
₹353 Cr
Total
₹353 Cr
0.0%
Utilized
Project Approved
Construction / Implementation
Original End Date
2026-03-26
Revised Completion
Completed
Project is within original budget of ₹353 Cr — no cost escalation recorded.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹353 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.