Original Cost
₹588 Cr
Baseline estimate
Revised Cost
₹588 Cr
Latest approved cost
Expenditure
₹37 Cr
Spent to date
Utilization
6.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹551 Cr
Budget left
Spent
₹37 Cr
Remaining
₹551 Cr
Total
₹588 Cr
Project Approved
Construction / Implementation
Original End Date
18/11/2026
Revised Completion
18/11/2026
Completed
Project is within original budget of ₹588 Cr — no cost escalation recorded.
Expenditure stands at ₹37 Cr, which is 6.4% of the revised project cost.
Remaining budget: ₹551 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.