Original Cost
₹955 Cr
Baseline estimate
Revised Cost
₹955 Cr
Latest approved cost
Expenditure
₹241 Cr
Spent to date
Utilization
25.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹715 Cr
Budget left
Spent
₹241 Cr
Remaining
₹715 Cr
Total
₹955 Cr
Project Approved
Construction / Implementation
Original End Date
18/01/2026
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹955 Cr — no cost escalation recorded.
Expenditure stands at ₹241 Cr, which is 25.2% of the revised project cost.
Remaining budget: ₹715 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.