Improvement and Up-Gradation of Existing Road to 4L PS from Km 88.750 to 123.650, from Start of Shahjahanpur Bypass to start of Shahabad bypass of NH 731Pkg.-2A
Original Cost
₹955 Cr
Baseline estimate
Revised Cost
₹955 Cr
Latest approved cost
Expenditure
₹371 Cr
Spent to date
Utilization
38.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹584 Cr
Budget left
Budget Utilization
38.9%Spent
₹371 Cr
Remaining
₹584 Cr
Total
₹955 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
18/01/2026
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹955 Cr — no cost escalation recorded.
Expenditure stands at ₹371 Cr, which is 38.9% of the revised project cost.
Remaining budget: ₹584 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Improvement and Up-Gradation of Existing Road to 4L PS from Km 88.750 to 123.650, from Start of Shahjahanpur Bypass to start of Shahabad bypass of NH 731Pkg.-2A is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹955.00 Cr, later revised to ₹955.34 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Improvement and Up-Gradation of Existing Road to 4L PS from Km 88.750 to 123.650"?
- Improvement and Up-Gradation of Existing Road to 4L PS from Km 88.750 to 123.650, from Start of Shahjahanpur Bypass to start of Shahabad bypass of NH 731Pkg.-2A is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹955 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹955 Cr has not been significantly revised. Expenditure: ₹371 Cr (38.9% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Improvement and Up-Gradation of Existing Road to 4L PS from is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618858. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Improvement and Up-Gradation of Existing Road to 4L PS from is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.