Improvement and Up-Gradation of Existing Road to 4L PS from Km 123.650 to 175.080, from Start of Shahabad Bypass to End of Hardoi bypass of NH 731 Pkg-2B
Original Cost
₹1102 Cr
Baseline estimate
Revised Cost
₹1212 Cr
Latest approved cost
Expenditure
₹540 Cr
Spent to date
Utilization
44.5%
Of revised budget
Cost Status
+10.0%
+₹110 Cr increase
Remaining
₹672 Cr
Budget left
Budget Utilization
44.5%Spent
₹540 Cr
Remaining
₹672 Cr
Total
₹1212 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1102 Cr
Revised Cost
₹1212 Cr
Increase
+₹110 Cr
Escalation
+10.0%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/11/2025
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹110 Cr (10.0%) from the original estimate of ₹1102 Cr.
Expenditure stands at ₹540 Cr, which is 44.5% of the revised project cost.
Remaining budget: ₹672 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Improvement and Up-Gradation of Existing Road to 4L PS from Km 123.650 to 175.080, from Start of Shahabad Bypass to End of Hardoi bypass of NH 731 Pkg-2B is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1102.00 Cr, later revised to ₹1212.26 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Improvement and Up-Gradation of Existing Road to 4L PS from Km 123.650 to 175.08"?
- Improvement and Up-Gradation of Existing Road to 4L PS from Km 123.650 to 175.080, from Start of Shahabad Bypass to End of Hardoi bypass of NH 731 Pkg-2B is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹1102 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1102 Cr and has been revised to ₹1212 Cr — a cost overrun of +10%. Expenditure to date: ₹540 Cr (44.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Improvement and Up-Gradation of Existing Road to 4L PS from is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618856. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Improvement and Up-Gradation of Existing Road to 4L PS from is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.