Original Cost
₹255 Cr
Baseline estimate
Revised Cost
₹148 Cr
Latest approved cost
Expenditure
₹104 Cr
Spent to date
Utilization
70.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹43 Cr
Budget left
Spent
₹104 Cr
Remaining
₹43 Cr
Total
₹148 Cr
Project Approved
Construction / Implementation
Original End Date
16/06/2026
Revised Completion
31/08/2026
Completed
Project is within original budget of ₹255 Cr — no cost escalation recorded.
Expenditure stands at ₹104 Cr, which is 70.6% of the revised project cost.
Remaining budget: ₹43 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.