RailwaysIPM · Central Project#705493

Hubli-Ankola 167 km

Ministry of RailwaysKarnataka
Revised Cost: ₹533 CrUtilization: 34.9%

Original Cost

₹5174 Cr

Baseline estimate

On budget

Revised Cost

₹533 Cr

Latest approved cost

Expenditure

₹186 Cr

Spent to date

Utilization

34.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹347 Cr

Budget left

Budget Utilization

34.9%
0%25%50%75%100%

Spent

₹186 Cr

Remaining

₹347 Cr

Total

₹533 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2005

Revised Completion

31/03/2030

Completed

Project Details

Project Code705493
SectorRailways
MinistryMinistry of Railways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹5174 Cr
Revised Cost₹533 Cr
Expenditure₹186 Cr
Original End Date31/03/2005
Revised Date31/03/2030

Project Intelligence

Project is within original budget of ₹5174 Cr — no cost escalation recorded.

Expenditure stands at ₹186 Cr, which is 34.9% of the revised project cost.

Remaining budget: ₹347 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Hubli-Ankola 167 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹5174.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Hubli-Ankola 167 km"?
Hubli-Ankola 167 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Karnataka. Original cost: ₹5174 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹5174 Cr and has been revised to ₹533 Cr — a cost overrun of -89.7%. Expenditure to date: ₹186 Cr (34.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Hubli-Ankola 167 km is under the Ministry of Railways in the Railways sector. Project code: 705493. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Hubli-Ankola 167 km is one of several Bihar projects tracked under the Railways sector on the IPM system.